As the summer heat has continued to hit the triple-digits here at Ozarks, construction nears its end on campus.
According to U of O Business Manager Darrell W. Williams, "We are pushing to have Trustee Hall, the General and Organic Chemistry labs, the Fitness Center, and the Aerobics areas ready by the end of next week." He said painting, floor coverings, light fixtures, science fume hoods, and cabinet installation are all underway in Smith-Broyles, and work on parking lot paving, concrete sidewalks, irrigation and landscaping should also be in progress in just a few days. Fitness equipment and Trustee Hall furnishings are scheduled to arrive on Monday. August 8.